๐Ÿ“ˆ Investment Vehicles ยท high relevance

What is Net Present Value (NPV)?

The difference between the present value of an investment's future cash flows and its initial cost, both measured using the investor's required rate of return as the discount rate.

Choose Your Path โ†’ pick your exam ยท adaptive prep

Definition

Net Present Value (NPV)

Investment Vehicles High Relevance

The difference between the present value of an investment's future cash flows and its initial cost, both measured using the investor's required rate of return as the discount rate. NPV = Present Value of Future Cash Flows โˆ’ Initial Investment Cost. A positive NPV means the investment is expected to earn more than the required return; a negative NPV means it costs more than it is worth; a zero NPV means the investment earns exactly the required return.

// EXAMPLE

An investment costs $10,000 today and is expected to pay $4,000 per year for 3 years. Discounted at a 6% required return, the present value of those cash flows is $10,692, giving an NPV of +$692. Because the NPV is positive, the investment is expected to earn more than the 6% required return and should be accepted.

// COMMON_CONFUSION

A zero NPV does not mean zero profit. It means the investment earns exactly the discount rate used to calculate it, no more and no less. Also commonly mixed up: NPV is expressed in dollars, while IRR is expressed as a percentage, and it is NPV (not IRR) that is the preferred decision method when the two disagree on mutually exclusive projects.

How is Net Present Value (NPV) tested on the exam?

  • Calculating NPV from a series of cash flows, a discount rate, and an initial investment cost
  • Applying the accept/reject decision rule based on whether NPV is positive, negative, or zero
  • Explaining what a zero NPV actually means (exactly the required return, not zero profit)
  • Choosing between NPV and IRR when the two methods disagree on mutually exclusive projects
  • Distinguishing NPV's dollar output from IRR's percentage output

Calculation example

Calculation Example

Scenario: An investment costs $10,000 today and is expected to generate cash flows of $4,000 per year for 3 years. The required rate of return is 6%.
Formula: NPV = Present Value of Future Cash Flows โˆ’ Initial Investment Cost
Steps:
  1. Discount the Year 1 cash flow: $4,000 / 1.06 = $3,774
  2. Discount the Year 2 cash flow: $4,000 / (1.06)^2 = $3,560
  3. Discount the Year 3 cash flow: $4,000 / (1.06)^3 = $3,358
  4. Total present value of cash flows: $3,774 + $3,560 + $3,358 = $10,692
  5. NPV = $10,692 (present value of cash flows) โˆ’ $10,000 (cost) = +$692
Result: The NPV is +$692. Because it is positive, the investment is expected to earn more than the 6% required return and should be accepted.

Picture NPV as a bathtub: the present value of future cash flows pours in, the cost of the investment drains out. Whatever's left in the tub is the NPV. Above the drain line is profit (accept); below it, you're underwater (reject).

Practice questions

Test your understanding with the questions below. Pick an answer to reveal the explanation.

Question 1

An investment adviser representative is evaluating a client's proposed real estate investment. The project requires a $50,000 outlay today, and the present value of its projected cash flows, discounted at the client's 8% required rate of return, comes to $46,500. Based on the NPV decision rule, what should the adviser recommend?

Question 2

Net present value (NPV) represents the difference between which two values?

Question 3

An investment costs $10,000 today and is expected to generate cash flows of $4,000 per year for 3 years. If the required rate of return is 6%, the net present value of this investment is closest to:

Question 4

All of the following statements about net present value (NPV) are accurate EXCEPT

Question 5

An analyst calculates a project's NPV at +$18,000 using the firm's 7% required rate of return. Which of the following statements are accurate?

1. The project is expected to earn more than 7%
2. The project should be accepted
3. The project's IRR must be exactly 7%
4. The $18,000 figure represents value created in today's dollars

Where does Net Present Value (NPV) appear on the Series 65 exam?

This term is tested in the following Series 65 exam topics:

Related study guides

Master Net Present Value (NPV) and 500+ exam concepts

CertFuel's adaptive learning system uses spaced repetition to help you retain key terms and pass your securities exam on the first try.

Choose Your Path โ†’ pick your exam ยท adaptive prep